2916914 - How to make availability control on budget for year carry forward

Symptom

Availability control for projects can't carry forward the budget to the next fiscal year.

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Post commitments on project
  2. Post commitments amounts in the next fiscal year

Cause

There are 2 types of budget availability control profiles.

Resolution

In SSCUI Maintain Budget Availability Control Profile for Projects (102413), you can see there is column "Time Range" for the profile setting.
Annual Budget - there is no budget carry forward.
Overall Budget - budget is valid all over the project life span.

Choose the proper profile according to your requirement.