Symptom
When trying to add a Work Package in the Project Management Time Sheet, the button Add Work Package is grayed out.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to the Project Management Work Center.
- Click Edit Time Sheet view.
- Click Button Manage My Worklist.
The button Add Work Package is grayed out.
Cause
This scenario is occurring because the Employee is a Service Agent. Service Agents are external employees and therefore not able to add work packages themselves.
Resolution
Currently this is the expected system behavior.
Keywords
Add Work Package, grayed out, Project Management, Time Sheet. , KBA , SRD-HR-TLM , Time and Labour Management , How To
Product