Symptom
You are unable to modify the planned hours for certain projects and for some resources in the availability calendar, because some fields in the availability calendar are grayed out. As a consequence, the project commitment is not evenly distributed over the whole project period.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Resource Management work center
- Click on Resource Search view
- Search for the relevant employee
- Click on Show Availability
- Navigate to the date
- Select the relevant period
- Note: It is not possible to modify a certain project. But other projects can be modified.
Resolution
You can try to reset the remaining commitment to evenly distribute the commitment over the project period in the following way:
- Go to Resource Management work center
- Click on Resource Search view
- Search for the relevant employee
- Click on Show Availability
- Select the relevant project
- Click on Reset Commitment
Note: It is important the select the relevant project. If you don't select the relevant project, the button Reset Commitment is grayed out.
Keywords
interne Mitarbeiter auf Projekte planen, Angaben der geplanten Stunden gegraut, Angaben der geplannten Stunden ausgegraut, planned hours grayed out, internal employees, plan projects, resource management, resource search, availability calendar, Verfügbarkeitskalendar, Ressourcensuche, Ressourcen Management, , KBA , SRD-HR-RPM , Resource Pool Management , Problem