2931191 - Is it possible to stop the running report in SAP Jam?

Symptom

  • Is there a way to stop the report if the report has been running for a long time?
  • Admin is not able to cancel report that is running for a long time

Environment

SAP Jam Collaboration

Reproducing the Issue

  1. Go to SAP Jam admin
  2. Expand Analytics
  3. Click Reports
  4. Select a Report
  5. Specify Date Range
  6. Click Request Report

Resolution

  • There is currently no way to stop the report manually.
  • There's a code logic in the SAP Jam for long running jobs to be killed automatically if they have been running more than 2 days. You would have to wait until it exceeds two (2) days.
  • It is recommended to run reports on short time range instead of running more than a week.

See Also

2406676 - Reports available in SAP Jam

Keywords

SAP Jam reports, cancel, stop the running report, long running reports, cancel report , KBA , LOD-SF-JAM-REP , Reports , Problem