Symptom
The duration calculated for the start time and end time under time entry is so huge.
Environment
SAP Cloud for Customer.
Reproducing the Issue
-
Go to the Service work center.
-
Go to the Tickets view.
-
Search and open ticket LMN (where LMN represent the ticket id).
-
Go to the Time Entries facet.
-
Here maintain the start time and end time as nn:mm (where nn:mm represent some non-zero value).
-
You can see the duration is showing as NNN (where NNN represent the duration value more than 24 hours).
Cause
In standard base on start time and end time, the duration is calculated.However if you manually enter the duration, it allows you to enter any value for duration.
Resolution
Manually entering the duration to any value is allow and this is current system behavior.