Symptom
While creating a production order the basic dates are specified by the user, but the system moves the end date back by one day.
"Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental."
Read more...
Environment
- SAP ERP Capacity Requirements Planning (PP-CRP)
- SAP R/3
- SAP R/3 Enterprise
- SAP ERP Central Component
- SAP ERP
- SAP Enhancement package for SAP ERP
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
Product
SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA all versions
Keywords
Work Center, Production Order, End Date, Start Date, CO01, CO02, CO03, Operation. , KBA , PP-CRP , Capacity Planning , PP-SFC , Production Orders , Problem