Symptom
When importing custom learning activities, the completed date will change to the imported date
Environment
SAP SuccessFactors Career Development Planning
Cause
Your system is integrated with LMS. This is by design for integrated instances. The purpose of the complete_date field is to record the status change date, so 'write' permission should not be given for this field.
Resolution
You can create a custom field for complete_date to record the date given in the import file. Please reach out to your partner/ consultant to have this configured.
Keywords
KBA , LOD-SF-CDP-LA , Learning Activity Plan (LMS) , How To
Product
SAP SuccessFactors Succession & Development all versions