Symptom
The configuration changes performed in the Quality (Q) system need to be transported to the Production (P) system.
Environment
SAP S/4HANA Cloud Public Edition
Resolution
This process is called the Q to P transport process. You control the Q to P transport process using the 'Manage Your Solution' and 'Configure Your Solution' apps in the Q and P system. You need to create a change project by choosing the option 'Create Change project' in app 'Manage your solution'. All changes made in SSC-UI will be captured in the current change project. After making the changes, you need to click 'Proceed to Run' button to start the transport.
Most of the changes in SSC-UIs can be transported in this way. Others need to confirm with application team - the owner of a specific SSC-UI.
See Also
2929962 - All changes made in SSC-UI will be captured in the current change project
2870608 - How to request the initial transport from Q to P
2707813 - SAP S/4HANA Cloud Public Edition: Configuration Transport import time to P system
2801917 - Error : BCP project not available, so app will be read-only
Keywords
SV-CLD-SSC, SSCUI, change project, configure, SV-CLD-FRM-APP, SAP S/4HANA Cloud Public Edition, S4_PC, sv-cld-frm-inf, Create Change project, deploy, Q2P, framework, transport , KBA , SV-CLD-FRM-INF , Implementation Framework Infrastructure , SV-CLD-SSC , Self-Service-Configurations-UI , How To