Symptom
When scheduling a maintenance plan with key date, if month is shorter than planned date the date is adjusted to last day of the month. Subsequent calls are also scheduled at this earlier date
Read more...
Environment
- SAP ERP Plant Maintenance (PM)
- SAP R/3
- SAP R/3 Enterprise
- SAP ERP Central Component
- SAP ERP
- SAP Enhancement package for SAP ERP
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
Product
SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions
Keywords
IP30, IP10, RISTRA20, IP19, IP30H, Leap year, Calendar, NPLDA , KBA , PM-PRM-MP , Maintenance Plans , Problem