SAP Knowledge Base Article - Preview

2947035 - Maintenance plan scheduling with Key Date and short month

Symptom

When scheduling a maintenance plan with key date, if month is shorter than planned date the date is adjusted to last day of the month. Subsequent calls are also scheduled at this earlier date

KeyDate.png


Read more...

Environment

  • SAP ERP Plant Maintenance (PM)
  • SAP R/3
  • SAP R/3 Enterprise
  • SAP ERP Central Component
  • SAP ERP
  • SAP Enhancement package for SAP ERP
  • SAP Enhancement package for SAP ERP, version for SAP HANA
  • SAP S/4HANA, on-premise

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

IP30, IP10, RISTRA20, IP19, IP30H, Leap year, Calendar, NPLDA , KBA , PM-PRM-MP , Maintenance Plans , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.