SAP Knowledge Base Article - Public

2947568 - Rolling Run Does Not Update Demand Plan

Symptom

Rolling Run ABC (ABC represents the Rolling Run ID regarding the issue) is not impacting on the date for Demand Plan XYZ (XYZ represents the Demand Plan ID regarding the issue).

Environment

 SAP Business ByDesign

Reproducing the Issue

  1. Go to the Demand Planning work center.
  2. Go to the Rolling Runs view.
  3. In the dropdown, select Active Rolling Runs.
  4. Search for Rolling Run ABC.
  5. In the dropdown, select Last 5 Logs.
  6. You will see the Run ID ABC and the last Application Log ID. 
  7. Click the Application Log ID XXX (XXX represents the Log ID regarding the issue).
  8. You will see that this Application Log ID is finished.
  9. Go to the Demand Planning work center.
  10. Go to the Demand Plans view.
  11. Select Demand Plan XYZ.
  12. Observing the Forecast Start Date, it should have moved to the next month. 

Cause

You have to enter Demand Plan XYZ in the Run ID ABC. With this information, system will consider and update the correct Demand Plan.

Resolution

  1. Go to the Demand Planning work center.
  2. Search for Rolling Run ABC.
  3. Select Run ID ABC.
  4. Click Edit.
  5. Under Selection Criteria Section, find the column Demand Plan ID From.
  6. Click the selection box.
  7. Enter The Demand Plan ID XYZ.
  8. Click Save.

Keywords

Rolling Run, Demand Plan , KBA , AP-DP-PPR , Demand Plan Preparation Run , How To

Product