Symptom
How to add future dated achievement in Continuous Performance Management
Environment
SAP SuccessFactors Continuous Performance Management
Cause
1.Log into instance
2.Go to continuous performance management
3.Go to achievements click add achievement.
4.Enter achievement date
Resolution
1.Log into instance
2.Go to continuous performance management
3.Go to achievements click add achievement.
4.Give achievement name, give achievement date as future dated
5.Click save, future dated achievement created successfully without any error or warning
NOTE: Achievement date of the CPM must be equal to or greater than the start date of the PM form.