Symptom
Error ME154 'Not possible to determine any components' happens when creating purchase order for subcontracting item category.
Environment
- Sourcing and Procurement
- SAP S/4HANA Cloud Public Edition
Reproducing the Issue
Create a PO with item category L.
BOM and Production version have been maintained.
Cause
The release date in PO is out of valid range of Production version.
Release date should be calculated as below:
Delivery date - Planned delivery time - Purchase processing time(working day) = Release date(Start date for planned order)
SSCUI/Activity 102156 can be used to check and maintain value of 'Purchase processing time'.
Resolution
Adjust the delivery date in PO or maintain a proper valiad range of Production version date.
See Also
Keywords
S4, HANA, ME154 , KBA , MM-PUR-PO , Purchase Orders , How To