Symptom
When posting timesheet on a WBS Element, the cost rate maintained with the WBS Element is not picked up.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
Enter timesheet for WBS Element with App My Timesheet App.
Check the cost rate used with App Display G/L Account Line Items.
Cause
The cost rate sequence can be found in the help portal:
https://help.sap.com/viewer/c56f622a2edf491b9f1b596b55587009/latest/en-US/9fca5b12d8df4591a240100305da6357.html
Check the Field Priority part.
The system will fetch available prices from top down.
If the prices on the top is not found, system will find lower one. Until it find the valid price.
Statistical WBS Element will not be considered during cost rate determination.
Resolution
Please check the tip in above same link:
Tip
You may find it helpful to use lower-priority fields early in your planning process, then higher-priority fields later as planning becomes more detailed. For example, you could enter the required service cost level early in the process, and later change this to a specific employee.
Keywords
Notify missing time, price, manage cost rate - professional services, ACCOSTRATE, work item, personal number, cost center, activity type, service cost level. , KBA , CO-OM-ACT-E-2CL , Postings (Public Cloud) , CA-TS-CO , Integration Controlling , CA-TS-S4 , Cross Application Timesheet in S/4HANA , Problem