2956896 - Project Invoice Request Not Created For a Sales Order With Project Milestone

Symptom

  • No Project Invoice Request is appearing for Sales Orders related to Project having Milestones. But directly an Invoice Request is created.
  • No Invoice Request is created at all through scheduled invoice.
  • When creating a Scheduled Invoice Request for a Milestone the following error message occurs: Scheduled invoice request not created; no relevant items found.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to the Customer Invoicing work center.
  2. Go to the Project Invoice Request view.
  3. Choose All Project Invoice Requests.
  4. Click on Advanced.
  5. Enter the Reference as Sales Order or Project.
  6. Click on Go button.

No details are appearing.

  1. Go to the Customer Invoicing work center.
  2. Go to the Invoice Requests view.
  3. Choose All Invoice Requests.
  4. Enter Project ID.
  5. Click on Go button.
  6. You get the Invoice Request. 

All sales order seems to be linked to project task because

  1. Go to the items tab of Sales Order. 
  2. Go to Cost and Revenue Assignment.
  3. You will see Project Task appearing.

Scheduled invoice request not created; no relevant items found.

  1. Go to the Project Management work center.
  2. Choose the Projects view and then the Projects sub view.
  3. Show All Projects and click the Go button.
  4. Select the Project ABC (ABC represents the project name).
  5. Click the Project Identifier icon, which is displayed under the Project ID column.
  6. Choose Create Scheduled Project Invoice Request.
  7. While creating the Scheduled Invoice Request error message occurs: Scheduled invoice request not created; no relevant items found.

Cause

The behavior is happening because of one of the following reasons:

  • Sales Order item type is not Project Based as mentioned on Milestone Invoicing for Customer Projects 
  • The error message occurs, because the Status of the Milestone to be invoiced is not set to Completed and  thus you cannot create a Scheduled Invoice Request
  • For every project it is allowed to have only one project invoice having status “In Preparation”. If there is another Project Invoice Request already added to the Project and this document has status In Preparation, the system will not create a new Project Invoice Request.

Resolution

Solution for above causes respectively:

  • In new Sales Orders, change your project type to 'Service fixed price - Project' or a type that has 'Project' in it.

For existing Sales Orders, you cannot make changes to item type so either leave them as they are or cancel and create new Sales Orders.

  • To maintain the Status of the Milestone you can use the following steps:
  1. Go to the Project Management work center.
  2. Choose the Projects view and then the Projects sub view.
  3. Show All Projects and click the Go button.
  4. Select the Project ABC.
  5. Click the Edit button and choose Project Plan.
  6. Select Milestone XYZ (XYZ represents the milestone name).
  7. Set the Status to Completed.
  8. Save changes.

 Now you shall not see error message when creating  a  Scheduled Invoice Request.

  • If you already have a Project Invoice Request with status "In Preparation", complete this first document and then create the new Project Invoice Request.

See Also

Keywords

Milestone invoicing, no project invoice request, not created, automatically, milestone, project, Project Invoice Request Not Created For a Sales Order , KBA , SRD-PRO-INV , Projects Customer Invoicing , AP-SLO , Sales Order Processing , How To