Symptom
You are trying to confirm the Design Acceptance milestone in your First Implementation project, but experience the following error message:
"Confirm Milestone: Design Accepted failed; retry or report an incident."
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Business Configuration work center.
- Go to Implementation Projects view.
- Select the First Implementation project.
- Click Open Activity List.
- Go to the Prepare tab.
- Open the activity Confirm Milestone: Design Accepted.
- Select Confirm.
System raises the mentioned error message.
Cause
You have scoped question "Do you want to enter supplier invoices via PDF scanning?", but PDF Invoice Scanning not supported from China Datacenter.
Resolution
Please descope the question "Do you want to enter supplier invoices via PDF scanning?" as below:
- Go to Business Configuration work center.
- Go to Implementation Projects view.
- Select the First Implementation project.
- Click Edit Project Scope.
- Navigate to step 4, Questions.
- Expand Purchasing, then expand Supplier Invoicing.
- Select the Supplier Invoices and Credit Memos option.
- In the right side of the screen, navigate to Entry of Supplier Invoices via PDF scanning.
- Uncheck question "Do you want to enter supplier invoices via PDF scanning?".