SAP Knowledge Base Article - Public

2971361 - Very High priority cases in SAP Datasphere

Symptom

Criterias for justified "Very High" priority ticket in SAP Datasphere

Environment

SAP Datasphere

Resolution

"Very High" priority is justified when:

  • Productive SAP Datasphere tenants can not be reached, see  SAP KBA 2882762 - Outage Information for SAP Datasphere
  • Imminent system go-live of a production tenant (for example, within the next five working days) is impacted, which would cause serious losses if not resolved before go-live.
  • Critical and productive Data Models, Stories, or replications that used to work properly are impacted by regression issues

"Very High" priority is NOT justified when:

  • Test/Development SAP Datasphere tenants can not be reached, see  SAP KBA 2882762 - Outage Information for SAP Datasphere
  • Tenant provisioning
  • Datasphere project is delayed
  • Connectivity with DP Agent can not be established 
  • New model or development is not working as expected
  • Enablement of features (a.k.a. Service Requests) involving DevOps

Very High priority requirements: