2974451 - MRP Live does not plan PP/DS materials despite "Changed BOM Components" flag

Symptom

  • You execute MRP Live (MD01n) for an Advanced Planning material with flag "Changed BOM Components" active
  • You expect that MRP Live will automatically extend the selection and plan as well the components which have been changed during the planning run, but this does not happen


Read more...

Environment

  • SAP S/4 HANA Release 1610, 1709, 1809, 1909, and follow up releases using the embedded PPDS functions 

Product

SAP S/4HANA 1610 ; SAP S/4HANA 1709 ; SAP S/4HANA 1809 ; SAP S/4HANA 1909 ; SAP S/4HANA 2020 ; SAP S/4HANA 2021 ; SAP S/4HANA 2022 ; SAP S/4HANA 2023

Keywords

COMPS, PLALL, ET_PLAN_MRP_COMP, LT_PLAN_MRP_COMP, SET_HEUR_MRP_COMPONENTS, D4, /SAPAPO/RRP_EVENT , KBA , SCM-APO-PPS-HEU , Heuristics , PP-MRP , Material Requirements Planning , Problem