Symptom
In customer project, when changing toggle of "Confirmed" from "ON" to "OFF", following error occurs.
"You cannot change the confirmation status, as time postings exist.".
It is unclear how the actual time postings are checked.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Go to app "plan customer project".
- Go to tab "Team".
- Change the toggle : "Confirmed" from "ON" to "OFF".
Resolution
When changing a confirmed resource to not confirmed, the system will check the actual time postings based on following criteria.
- Work Package ID
- Work Item ID
- Resource ID
- Employee ID
Keywords