Symptom
You create a WBS in Project Builder app with an Responsible cost center and set status to released. WBS Company code is derived from the cost center. Later on, you change the company code of the cost center. The company code of the WBS stays as the old one, and when changed the error message is raised:
The Responsible Cost Center assigned should have the Company Code XXXX.
Read more...
Environment
SAP S/4HANA Cloud.
Product
SAP S/4HANA Cloud all versions
Keywords
WBS element , KBA , PS-ST-WBS , Work Breakdown Structure , Problem