3019952 - Detailed scheduling date is not changed automatically in production order

Symptom

When using API API_PRODUCTION_ORDER_2_SRV/A_ProductionOrder_2 to change Basic Dates of production order, the scheduled dates are not changed.
The same symptom occurs when trying to change the production order directly in app "Change Production Order" (CO02).

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Using API API_PRODUCTION_ORDER_2_SRV/A_ProductionOrder_2 to change MfgOrderPlannedStartDate or MfgOrderPlannedEndDate.
  2. MfgOrderScheduledStartDate and MfgOrderScheduledEndDate are not changed accordingly. 

Cause

SSCUI 102448 has not been maintained or the "automatic scheduling" indicator is OFF.

Resolution

Go to SSCUI 102448 to maintain Scheduling Parameters for Production Orders and make sure that the "automatic scheduling" indicator is ON.

Keywords

API API_PRODUCTION_ORDER_2_SRV, A_ProductionOrder_2, MfgOrderPlannedStartDate, MfgOrderPlannedEndDate, automatic scheduling, MfgOrderScheduledStartDate, MfgOrderScheduledEndDate, schedule order, basic dates, start date, end date, scheduled date, scheduled,  auto scheduling, change production order, CO02 , KBA , PP-SFC-EXE , Order Execution , PP-SFC-EXE-2CL , Order Execution (Public Cloud) , Problem

Product

SAP S/4HANA Cloud Public Edition all versions ; SAP S/4HANA Cloud all versions