3023289 - System Doesn't Calculate Work Packages in the Resource Calendar

Symptom

When looking at the employee resource calendar, project work packages are not taken into consideration.

Environment

SAP Business ByDesign

Reproducing the Issue

1. Go to Work Center Employee Resource Calendar

2. Search for the relevant employee

2. Observe that for this employee some work packages are missing

Cause

If you have entered less than 15 minutes per day in the planned hours, the distribution of the hours will not happen.

Resolution

Enter at least 15 minutes per day for the work packages to be shown in the resource calendar.

Keywords

Wrong calculation, employee availability, calendar , KBA , SRD-HR-RPM , Resource Pool Management , Problem