Symptom

In Manage Project Billing app, the amount "To Be Billed" is positive even if negative time recordings were posted .

Environment

SAP S/4HANA Cloud

Reproducing the Issue

  1. Post negative time recording for a resource assigned to customer project. 
  2. Go to Manage Project Billing app to check the "To be billed" amount.
  3. The amount is showing as positive.

Cause

The price of the resource is maintained as negative in Manage Prices - Sales app.

Resolution

Change the price to positive then post new time recording.