3033608 - System allows the creation of a WBS number diverging from Project ID

Symptom

When creating new WBS you are able to create a WBS that diverges from project ID. For example

Project ID is T.22.1111

You are able to create a WBS ID as T.22.0001

Environment

SAP S/4HANA Cloud.

Reproducing the Issue

  1. Go to project control app.
  2. Select a project.
  3. Click Edit in and select project planning.
  4. Create a new WBS diverging from project ID. 

Cause

This is the standard behavior of the system.

Resolution

This is the standard behavior of the system and currently there is no validation for the WBS ID to be equal to the project.

If you would like to have a validation of this kind, you may implement a BADI to adequate to your requirements.

The below URLs present some of the extensibility possibilities that you may use:

App Extensibility: Project Planning

App Extensibility: Project Builder

See Also

App Extensibility: Project Planning

App Extensibility: Project Builder

Keywords

Project Control, planning, work breakdown structure , KBA , PS-FIO-STR , Fiori UI for Project Systems-Structures , PPM-FIO , Fiori UI for Portfolio and Project Management , Problem

Product

SAP S/4HANA Cloud Public Edition all versions ; SAP S/4HANA Cloud all versions