SAP Knowledge Base Article - Public

3041528 - The BOM of phantom assembly can be exploded in Production order but cannot be exploded in planned order.

Symptom


The BOM of phantom assembly can be exploded in Production order but cannot be exploded in planned order.

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Use app Create Planned order or run MRP to create planned order.
  2. The BOM of the phantom material cannot be exploded.
  3. When using app Create Production Order to create production order, the BOM of phantom material can be exploded successfully.

Cause

There is no production version maintained for the phantom material.
The logic for BOM explosion under Production order creation and Planned order creation area is different .
During a planned order creation, a check is performed on the production version for phantom assemblies. In this case the production version must be maintained.
During a production order creation, system goes through the bill of material maintained for the header material and explodes all components. A production version is required here, but only for the header material, not for the components.

Resolution

Maintain production version for phantom material.

Keywords

Could not explode phantom assembly, MD511, planned order, component, production order, process order, phantom, phantom assembly, BOM, BOM explosion, MRP, MD11, CO01
, KBA , PP-SFC , Production Orders , PP-MRP , Material Requirements Planning , PP-SFC-2CL , Production Orders (Public Cloud) , Problem

Product

SAP S/4HANA Cloud Public Edition all versions