Symptom
Production order/process order is with zero target costs.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
Check order target costs via App Event-Based Order Costs.
Cause
There could be several reasons for the issue:
- There is no actual goods receipt (GR).
- There is no valid standard cost estimate for the production material.
Resolution
Standard cost estimate is the foundation for target costs. If there is no valid standard cost estimate when creating the production order/process order, system can't calculate target costs.
It's necessary to have standard cost estimates. If business needs the validation to raise error when there is no standard cost estimate during order creation, below blog post can be referred to:
How to Get Manufacturing Orders Check Whether Header Materials Have Released Standard Costs