SAP Knowledge Base Article - Public

3045486 - Production order/process order is without target costs

Symptom

Production order/process order is with zero target costs.

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

Check order target costs via App Event-Based Order Costs.

Cause

There could be several reasons for the issue:

  • There is no actual goods receipt (GR).
  • There is no valid standard cost estimate for the production material.

Resolution

Standard cost estimate is the foundation for target costs. If there is no valid standard cost estimate when creating the production order/process order, system can't calculate target costs.

It's necessary to have standard cost estimates. If business needs the validation to raise error when there is no standard cost estimate during order creation, below blog post can be referred to:

How to Get Manufacturing Orders Check Whether Header Materials Have Released Standard Costs

Keywords

zero, target cost, blank, event-based, order costs, variance, validation, creation, error, standard cost estimate. , KBA , CO-PC-OBJ-2CL , Cost Object Controlling (Public Cloud) , PP-SFC-2CL , Production Orders (Public Cloud) , Problem

Product