Symptom
User expects the Planned Delivery Time of the contract to be determined based on Material Master instead of the info record, since the 'Scheduling: Info Rec/Agreemt' indicator is not set.
Read more...
Environment
Materials Management (MM)
- SAP ERP Central Component
- SAP ERP
- SAP enhancement package for SAP ERP
- SAP enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA
Product
SAP ERP all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions
Keywords
ECC, contract, planned, delivery, time, indicator, 'Scheduling: Info Rec/Agreemt', material, master, info, record, scheduling, OPPQ , KBA , MM-PUR-OA-CON , Contract , Problem