3057265 - How to view multiple materials cost component

Symptom

You want to view cost component of multiple materials.

Environment

SAP S/4HANA Cloud

Resolution

1. Open APP Material Cost estimates, enter a plant and choose ''Execute''.
2. Choose ''Current Display Variant''(shown as two overlapping squares) on the top of the screen.
3. Choose ''Position'' and choose the hidden fields including the ''Direct Material, Credits (Co/By-Pr)Cr, Third Party, Material Overhead, etc.''.
4. Add these fields to left position by clicking button ''<'', then click ''Copy''.
Then you can view multiple materials cost component, you can also save the changed layout by clicking ''Save''.

Keywords

Material cost estimate; cost component; CK11n; CK82. , KBA , CO-PC-PCP-WQS , Product Costing with Quantity Structure , CO-PC-PCP-WQS-2CL , Product Costing with Quantity Structure (Public Cloud) , Problem