3060984 - Warning message "Reord.Point w/ Ext.Req and Repl to Max Stock is not supported in MRP Live" after running MRP

Symptom

When running MRP for materials with the combination of Reorder Point and Replenishment to Max Stock Level, below warning message was triggered.
"Reord.Point w/ Ext.Req and Repl to Max Stock is not supported in MRP Live"

Environment

SAP S/4HANA Cloud 

Cause

The warning message is just an info text that planning was scheduled in classic MRP rather than MRP live . It won't affect the MRP result.

Resolution

You may use the filter (e.g. Category ) to exclude such warning messages if you would like to get them not shown up.

Keywords

Display MRP Master Data Issues, Reord.Point w/ Ext.Req and Repl to Max Stock is not supported in MRP Live, reorder, max stock, HB, V1 , KBA , PP-MRP , Material Requirements Planning , PP-MRP-2CL , Material Requirements Planning (Public Cloud) , Problem

Product

SAP S/4HANA Cloud Public Edition all versions ; SAP S/4HANA Cloud all versions