Symptom
You have set the Advanced Planning flag (MARC-PPSKZ) in material master and also the Plan in Classic MRP (PLAN_IN_ABAP) in MD_MRP_FORCE_CLASSIC. You expect that the flag Plan in Classic MRP could prevent the material to be sent to PP/DS planning and plan the material in classic MRP.
However, the material is planned by PP/DS. In this case it is not clear which flag has higher priority.
Read more...
Environment
- SAP ERP Production Planning (PP)
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
Product
Keywords
MD01N, MRP Live, PP/DS, heuristic, MD_MRP_FORCE_CLASSIC, Classic MRP, ABAP, PP/DS, Advanced Planning, MARC-PPSKZ, PLAN_IN_ABAP, MM02, MD03, Material Master , KBA , PP-MRP-PR , Planning Execution , How To