SAP Knowledge Base Article - Public

3062083 - No value in Future Cost Estimate in Material Master even Cost Estimate is marked

Symptom

You have finished Marking step with App Edit Costing Run. After that, you check App Display Material Master - Tab Costing 2 and found the Future Cost Estimate field is not filled.

Environment

SAP S/4HANA Cloud

Reproducing the Issue

Check field Future Cost Estimate in App Display Material Master.

Cause

After CE2105, with Parallel Accounting introduced, the material cost estimates are ledger enabled. The Future Cost Estimate field is only filled is the cost estimate is marked for the leading ledger.

Resolution

With App Edit Costing Run, in General Data setting - Costing data tab, there is field "Ledger". If you don't intend to mark/release for specific ledger, you should leave the field as blank.

In Processing setting, in the Authorization column, you could see a lock button with name "Allowed". In this Marking Allowance setting, you should update all the ledgers.

Keywords

cost estimate, future, released, marked, 0L, 2L, ledger , KBA , CO-PC-PCP , Product Cost Planning , CO-PC-PCP-2CL , Product Cost Planning (Public Cloud) , Problem

Product

SAP S/4HANA Cloud Public Edition all versions