3068721 - Import Job Next Scheduled refresh shows wrong date and time in SAP Analytics Cloud (SAC)

Symptom

The following behavior occurs in SAP Analytics Cloud (SAC):

  • Next refresh date of scheduled import jobs displays "01.01.1970" or "31.12.1969"

Environment

  • SAP Analytics Cloud 2021.7.7

Reproducing the Issue

  1.  Open a Model with Import Jobs
  2.  Open the Query properties
  3.  Check the Next Schedule Refresh date, it shows "01.01.1970" or "31.12.1969"

Cause

This is a known defect

Please note: the schedules will run at the preset date

Resolution

This issue will be fixed in QRC3 

See Also

Keywords

SAP Cloud for Planning, sc4p, c4p, cforp, cloudforplanning, Cloud for Analytics, Cloud4Analytics, CloudforAnalytics, Cloud 4 Planning, BOC, SAPBusinessObjectsCloud, BusinessObjectsCloud, BOBJcloud, BOCloud., SAC, SAP AC, Cloud-Analytics, CloudAnalytics, SAPCloudAnalytics,Error, Issue, System, Data, User, Unable, Access, Connection, Sac, Connector, Live, Acquisition, Up, Set, setup, Model, BW, Connect, Story, Tenant, Import, Failed, Using, Working, SAML, SSO, sapanalyticscloud, sap analytical cloud, sap analytical cloud, SAC, sap analyst cloud, connected, failure, stopped
, KBA , LOD-ANA-AQU , Import Data Connections (Acquiring Data) , LOD-ANA-SCH , SAC Story Scheduling and Publication , Known Error

Product

SAP Analytics Cloud 1.0