Symptom

You have maintained task generation method as Reporting Point including Operations and Activities.

However, you find one of the production tasks doesn't take the description you maintained in element type Reporting Point.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Production Control work center.
  2. Go to Task Control view.
  3. Show all and search task ABC (ABC represents the task ID).
  4. You find the task description is not the one you maintained in element type Reporting Point.
  5. Instead, system takes the description of Quality Check Activity from Bill of Operation structure in the corresponding production model.

Cause

This is a quality check task, this is independent of the task generation method. It is always created as the last operation in the Bill of Operations.

No further operation can be created after this operation and it always consists of only one activity.

Hence, system takes the description of its activity and maps it to the production task.

Resolution

This is expected system behavior.