Symptom

Conversion between Order UOM and Planning UOM cannot be batch dependent error message in customer demand.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Outbound Logistics Control work center.
  2. Navigate to Customer Demand view.
  3. Search for the relevant customer demand, select a line item and choose Edit button.
  4. Choose the line item which you need to release and from the Actions button select the option Check Availability. 

The reported error message is displayed.

Cause

  • ATP shall not consider batches while giving confirmations and ATP uses planning UOM as the basis for its confirmation.
  • Since the ATP considers only stock independent of batch for availability confirmation, the unit of measure maintained in planning and the unit of measure used in sales order should not be batch dependent. 

Resolution

System behavior is the result of incompatible setting maintained in product master data. This is not a bug in the system.

See Also

Blog explaining Batch Specific Conversions in SAP BusinessByDesign

Keywords

Conversion between planning UOM and Order UOM cannot be Batch dependent, Warning message appears "Conversion between planning UOM and Order UOM cannot be Batch dependent" , KBA , batch dependent uom , batch dependent uom error , AP-CR-CR , Customer Requirement , Problem

Product

SAP Business ByDesign all versions