Symptom
Changing the MRP lot size to a lot size that is dependent on a planning calendar, the system does not issue the warning message:
"Maintain the planning calendar for the plant or its reference plant" - Message no. MM221
Image/data in this KCS is from SAP internal systems,sample data, or demo systems. Any resemblance to real data is purely coincidental.
Read more...
Environment
- SAP ERP Logistics (LO)
- SAP Enhancement package for SAP ERP
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
Product
SAP ERP 6.0 ; SAP S/4HANA 1709 ; SAP S/4HANA 1809 ; SAP S/4HANA 1909 ; SAP S/4HANA 2020 ; SAP S/4HANA 2021
Keywords
OMT4, OMI4, MM 221, MRP1, MRP2, Planning calendar, MRP Lot Size, Period lot size acc. to plng calendar, MARC-DISLS, MARC-MRPPP, T160M , KBA , LO-MD-MM , Material Master , Problem