3109384 - Local client copy scheduled to run as tasklist does not start

Symptom

  • You are trying to schedule a local client copy to run periodically using option "Execute as Tasklist"
  • When the scheduled job runs, the client copy does not start and the job log shows:  Task list run execution ended with status 'Stopped'
  • The task list run logs (t-code STC02 for task list SAP_CLIENT_COPY_LOCAL) show the following errors:
    • No value provided for mandatory parameter P_SCLNT (Source Client (Local Client))
    • No value provided for mandatory parameter P_TCLNT (Target Client)


Read more...

Environment

SAP S/4HANA 1909 and higher


Product

SAP S/4HANA 1909 ; SAP S/4HANA 2020 ; SAP S/4HANA 2021

Keywords

Execute as Tasklist, task list, background, foreground, local copy, sccln, SAP_CLIENT_COPY_LOCAL  , KBA , BC-CTS-CCO , Client Copy (For ByD issues select BC-TLM-CP) , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.