SAP Knowledge Base Article - Public

3126574 - After running MRP, the available quantity is still negative.

Symptom

After running MRP, no sufficient proposals (e.g. Planned order, purchase requisition) were generated.
i.e. the available quantity is still negative.

Environment

SAP S/4HANA Cloud

Cause

Please check whether you are using safety stock and in SSCUI 102373, 'Share of safety stock' has been set greater than 0 in field 'Avail. safety stock'.
If the MRP-relevant portion of safety stock is sufficient for covering the requirements, the system does not create any new proposals.

Resolution

Reset the portion of shared safety stock then run MRP again. 

Keywords

shared safety stock, Share of safety stock, Avail. safety stock, MRP group, safety stock, schedule MRP run, no proposal , no planned order, no purchase requisition, still negative, negative,  102373 , KBA , PP-MRP-PR , Planning Execution , Problem

Product

SAP S/4HANA Cloud all versions