SAP Knowledge Base Article - Public

3142299 - Is it possible to limit the goal's start & due date to the default dates configured in the Goal Plan?

Symptom

Is it possible to limit the goal's Start date and Due date to the default dates configured in the Goal Plan

Environment

SAP SuccessFactors Goal Management

Reproducing the Issue

In the latest goal management, when a user adds or edits a goal and select the start and due date.

Example : when Default due date is 12/31/2022, system will not allow user to select date beyond 12/31/2022. Similarly, when start date is 01/01/2022, system will not allow user to select date before 01/01/2022.

In the legacy version of goal management there is no possibility to limit the start & due date of goal as per the default start & due date of the goal plan template.

Resolution

The start & due date of the goal, this fields are auto populated with the start & due date defined in the goal plan due element.

But the system will not limit the end user to select a date that exceed the default due date when creating or editing a goals. Similarly for start date it will not allow the before dates.

This is only applicable in the latest version of goal management.

See Also

2645537 - Set the Default Start and Due Date for Goal Plan Template - Goal Management 

Keywords

Default due field, Goal Plan due date , Due , date , start , exceed , before , after , goal plan , field , Latest goal management , Legacy goal Management , auto populated , creating , editing , limit , KBA , LOD-SF-GM-ADM , Admin Tools, Settings, Permissions , How To

Product

SAP SuccessFactors Performance & Goals 2411