Symptom
The unit of lead time(parameter LEADTIME_UNIT) has been defined as DAYS. However after running heuristic, the Lead Time in days is calculated incorrectly in calendar weeks/Months.
For example, the heuristic is ran with 28 days of lead time. The expectation is to have lead time of four calendar weeks as 7 going into 28 four times. But the heuristic takes 28 days lead time of three calendar weeks in the result, which contains 21 days only.
Read more...
Environment
- SAP Sales and Operations Planning (SCM-SOP)
- SAP Integrated Business Planning (SCM-IBP)
Product
Keywords
lead time, technical week, calendar week, split, optimizer, heuristic, wrong, incorrect , KBA , SCM-IBP-SUP-ALG , Algorithms , SCM-IBP-SUP , Supply , Problem