3160029 - Due date is not shown in the task list in Process Governance

Symptom


I don't see any due date for my tasks or they are shown not correctly.



Resolution


There is no automatic due date. You have to define it first in the task. In the process, navigate to the task and click on 'Reminders'. First option is 'Due date'. Select the amount of days to define that. The change will be active for new started cases, you need also to publish changes.