Symptom
January Carry Forward balances are not being executed when we run Top node level G_Total. Job is failing.
runtime dumps.
STRING_SIZE_TOO_LARGE
Cannot extend the DB limit more than 2GB. Already checked with our basis team.
Only G_TOTAL is failing
When we run individual entities/ regions they are successful. When we run top node G_total it is failing.
Category ABAP programming error
Runtime Errors STRING_SIZE_TOO_LARGE
ABAP Program CL_SQL_STATEMENT==============CP
Application Component BC-DB-DBI
Read more...
Environment
SAP_BASIS 750 0008 SAPK-75008INSAPBASIS SAP Basis Component
SAP_UI 750 0008 SAPK-75008INSAPUI User Interface Technology
SAP_BW 750 0008 SAPK-75008INSAPBW SAP Business Warehouse
Product
Keywords
KBA , EPM-BPC-NW-TDL-BCF , Balance carry forward , Problem