Symptom
You wish to create a STR (Stock Transfer Requisition) between plants manually via tcode MD11 by using a special procurement key (SOBSL).
However, MD11 Special procurement type (SOBSL field) is changed from "STO" to "standard external procurement". Result is that requirements are not created in the correct plant.
Pre-requisites:
- You are using a special procurement scenario to produce in an alternative plant, that is, planning and production plant are different.
- The material is maintained in both plants.
- Storage locations maintained for the material are different in both plants.
- You are working with MRP area storage locations. This MRP area storage location is sourced via different a plant.
Read more...
Environment
- SAP S/4HANA
- SAP ERP
- Material Requirements Planning (PP-MRP)
Product
Keywords
KBA , PP-MRP , Material Requirements Planning , Problem