SAP Knowledge Base Article - Public

3209847 - Error: Data migration complete: New legacy fixed assets not possible during migration of Fixed Assets

Symptom

When attempting to migrate Fixed Assets, you are facing the Error: Data migration complete: New legacy fixed assets not possible.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Business Configuration
  2. Overview
  3. Migration of Accounting Transaction Data
  4. Execute migration for the Fixed Assets and Simulate All Records

Result Error: Data migration complete: New legacy fixed assets not possible

Cause

The process control is only open between posting dates XXX and YYY(XXX and YYY represent the posting dates). However the posting date of this migration unit is ZZZ so it prevents the migration to finish successfully.

Resolution

Example: The posting date maintained for the migration unit is 01.02.2022.

In the General Ledger Companies view , the process control is only open between the posting dates 29.01.2022 and 30.01.2022.

You need to modify the process control to include the posting date of the migration unit, here 01.02.2022.

Keywords