SAP Knowledge Base Article - Public

3213947 - Lease Contract: System Crashes When Selecting Cost Center

Symptom

In a lease contract you add a new cost center. But an Internal Server error message appears after selecting the cost center.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to the Lease Contract Management work center.
  2. Go to the Lease Contract view.
  3. Open the respective Lease Contract.
  4. Go to the Leased Objects tab.
  5. Go to the Organizational Assignments sub tab.
  6. Click Add Row.
  7. Select Cost Center ID AAA (AAA means the Cost Center ID).
  8. An internal server error appears. 

Cause

1. Cost Center ID AAA is not valid on the Lease Contract Start Date.

  • For example, the Lease Contract Start Date is 01.10.2018 and the Cost Center ID AAA is valid from 01.01.2020.

2. The selected Cost Center does not have a derivable Profit Center.

  • Go to Organizational Management work center
  • Go to Org Structures view.
  • There is no derivable profit center for the selected cost center.

Resolution

1. There are two options to solve the issue:

  • Change the validity of Cost Center ID AAA to embrace the start date of lease contract.
  • Change the start date of the lease contract to embrace the validity of the Cost Center ID AAA.

SAP is working to treat this code exception so the system does not crash but raise an error message.

2. Customer need to maintain at least one derivable profit center for the selected cost center.

Keywords

lease contract; cost center; start date; valid from; dump; crash; exception; DET_ORG_ASSIGNMENT_NODE; CL_FIA_LEASE_CO; Message E FIA_FD_ACCESS 015 cannot be processed in plug-in mode , KBA , AP-ACC-LM , Accounting Lease Management , SRD-FIN-FA , Fixed Assets , How To