Symptom

You have added an Input Product in a relevant Production Proposal however when you release a Production Order and check the relevant supply task, you find that added Input Product is missing.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to the Production Control work center.
  2. Go to Task Control view.
  3. Search for required Supply Task ID generated.
  4. Select and edit it, here in the Line items tab.
  5. You find that added input product is missing.

Cause

Since you have added a new row deleting the old one, then added an input product hence it is not available in a supply task however it is available in a make task.

Resolution

To add a new input product to the existing production proposal to have it in the supply task, follow the below steps:-

  1. Create a New Production Proposal.
  2. Go to the Supply Control work center.
  3. Go to the Process Production Proposals view.
  4. Find and select the relevant Production Proposal.
  5. Click the Edit button.
  6. Navigate to the Products tab, and then to the Input Product sub-tab.
  7. Here do not delete the existing row.
  8. Instead, replace the existing input product with a new one in the same row.
  9. Perform Save.