Symptom
You create purchase requisition/purchase order and expect commitment to be generated. However, the commitment generation is not successful.
If you check app Project Budget Report, the data for commitment is blank if you enter the relevant project.
Or you even the commitment is over the budget planned, there is not error when creating PR/PO.
Read more...
Environment
SAP S/4HANA Cloud
Keywords
PR, purchase requisition, balance sheet, account, cost element, commitment, not updated, zero, blank, project budget report, blank, no data, zero, no value, account assignment category, account assignment type, Q, budget check, Project Commitments, 2I3. , KBA , FI-PRA-2CL , Predictive Accounting (Public Cloud) , Problem
About this page
This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).Search for additional results