3230473 - Task from a Project Demand not showing in Manage my Timesheet

Symptom

You maintained a project demand for an employee, however the demand does not show in manage my timesheet.

 

Environment

SAP S/4HANA Cloud

Cause

  • Demand is not in status requested.
  • WBS is not released.
  • Demands  and WBS dates are outside of the Employment of the employee.

Resolution

Please check if you executed all of the following requirements

  • Maintain the Demand and WBS dates to be within the employee employment dates.
  • Released the WBS.
  • Set the status of the demand to Requested.

Keywords

KBA , PPM-SCL-DMN , Project Demand (Public Cloud) , CA-TS-S4 , Cross Application Timesheet in S/4HANA , Problem