3234000 - In Review Customer Projects app the date is shifted by 1 day

Symptom

The duration of a customer project created using the Create/Plan Customer Projects app may get offset by a day in the Review Customer Projects app header, based on the time zone settings of your Fiori Launchpad.

Environment

SAP S/4HANA Cloud 2208.

Reproducing the Issue

  1. Open Create/Plan Customer Projects app
  2. Create a new customer project
  3. Select the project duration
  4. Save the project
  5. Set the stage to Contract preparation
  6. Navigate to Billing section
  7. Add a billing item
  8. Set the stage to In Execution
  9. Navigate to the Review Customer Projects app
  10. Set the forecast month
  11. Navigate to Details page 
  12. View the duration of the project, which may get offset by a day in the app header, based on the time zone settings of your Fiori Launchpad

Cause

With CE2208, a new feature has been introduced by SAPUI5 to take into consideration the time zone configured by the user in Fiori Launchpad settings.

Previously only the time zone of the browser was considered.

 

Resolution

Please follow the resolution described in the following KBA:
3231384 - Chosen date in Date Picker is shifted - SAP S/4HANA Cloud 2208

See Also

3231384 - Chosen date in Date Picker is shifted - SAP S/4HANA Cloud 2208

Keywords

KBA , CA-CPD-SS , S/4HANA Public Cloud – Professional Service Projects , Problem

Product

SAP S/4HANA Cloud 2208