Symptom
I would like to split resources into working days. Is there possibility to expand and detail the resource allocation?
Resolution
You can adjust the resources and add e.g. Saturday to a specific role. To change that go to 'Scenarios' -> 'Resources'. Then you have to click on work schedules and add some working hours:
It is not possilbe to show this detailed information in the simulation excel export. Our product management has been already informed about it. If you want inform yourself about the status, please refer in the support email to ticket number PM-270.
Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental.
Keywords
KBA , BPI-SIG-PM-MOD-SIM , Simulation for SAP Signavio Process Manager , How To