Symptom
Cost rate for the project displays zero
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to the Project Management workcenter
- Projects view
- Select the project and navigate to the task
- On this project task go to the work task and see that for employee and the cost rate is zero
Cause
Cost valuation is executed for internal employees(employees belonging to the project company)
Resolution
In the project, the employee is involved as a service performer for supplier
That is why cost is not calculated.