Symptom
You have maintained a material in several storage locations within a plant, for example, some for production and some for storage.
You want to know what's the checking scope (plant level or storage location level) of the ATP check for the planned orders in which the material is a component.
Also, you want to adjust the checking scope and make the ATP check result as you want based on your business needs.
*Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental.
Environment
SAP S/4HANA Cloud Public Edition
Resolution
To change the checking scope, there are 2 main steps.
1. Check in the planned order what's the ATP checking rule. Open the corresponding planned order and do the following steps:
Now we can see "SR-P1" is the checking rule of this planned order.
2. Find the checking rule in SSCUI 101009 - Configure Scope of Availability Check and change it:
The indicator "Without Storage Location Check" controls the checking scope. If you set this indicator, the ATP check will be carried out on a plant level. Otherwise, only the production storage location will be considered. You can adjust it based on your business needs.
Keywords
ATP check, planned order, checking rule, checking scope, plant level, storage location level, SSCUI 101099, Without Storage Location Check , KBA , PP-SFC-PLN-2CL , Order Planning (Public Cloud) , PP-FLW , Flow Manufacturing , CA-ATP , Available to Promise (ATP) , How To